Zakon o potvrđivanju Ugovora o kreditnom aranžmanu br. CRS 1029 01 N između Francuske agencije za razvoj i Republike Srbije

Status propisa

Na snazi

Prikazana Verzija

Nema dostupnih verzija

Opšte Informacije

DonosilacNarodna skupština Republike Srbije

Član 12.2 Zakon o potvrđivanju Ugovora o kreditnom aranžmanu br. CRS 1029 01 N između Francuske agencije za razvoj i Republike Srbije – Progress Report

Section12.2

Progress Report

During the implementation of the Project, the Borrower shall supply to the Lender the Project progress reports in the format and content defined under the EBRD Loan Agreement and any relevant Project Document. Within three (3) months after the Technical Completion Date, the Borrower shall supply to the Lender a general progress report including a follow-up report with respect to the Project’ indicators in the form set out in Schedule 6 (Form Of Follow-Up Report Of The Project Indicators).