Zakon o potvrđivanju Ugovora o zajmu (Projekat izgradnje brane sa akumulacijom Pambukovica) između Republike Srbije i Evropske banke za obnovu i razvoj
Status propisa
Na snazi
Prikazana Verzija
Nema dostupnih verzija
Opšte Informacije
Donosilac
Narodna skupština Republike Srbije
Član Section 2.03. Zakon o potvrđivanju Ugovora o zajmu (Projekat izgradnje brane sa akumulacijom Pambukovica) između Republike Srbije i Evropske banke za obnovu i razvoj – Drawdowns
The Available Amount may be drawn down from time to time in accordance with the provisions of Schedule 2 to finance (1) expenditures made (or, if the Bank so agrees, to be made) in respect of the reasonable cost of goods, works and services required for the Project, and (2) the Front-end Commission.
b)
The Borrower hereby authorises the Bank to draw down from the Available Amount an amount equal to the Front-end Commission and pay to itself the Front- end Commission on behalf of the Borrower.