ARTICLE IVČl. Section 4.01.–Section 4.02.

SUSPENSION; ACCELERATION; CANCELLATION

Član4.01.

Suspension

The following are specified for purposes of Section 7.01(a)(xvii) of the Standard Terms and Conditions:
a)
The legislative and regulatory framework applicable to the irrigation and construction sector in the territory of the Borrower shall have been amended, suspended, abrogated, repealed or waived in a manner other than as approved by the Bank in writing;
b)
The Statutes shall have been amended, suspended, abrogated, repealed or waived; and
c)
Control of the Project Entity shall have been transferred to a party other than the Borrower.
Član4.02.

Acceleration of Maturity

The following are specified for purposes of Section 7.06(f) of the Standard Terms and Conditions:
a)
any event specified in shall have occurred and shall have continued without remedy for thirty (30) days after notice thereof shall have been given by the Bank to the Borrower.