Section11.6

Environmental and social responsibility

11.6.1 Implementation of environmental and social measures
In order to promote sustainable development, the Parties agree that it is necessary to promote compliance with internationally recognised environmental and labour standards, including fundamental conventions of the International Labour Organization (“ILO”) and the international environmental laws and regulations applicable in the Borrower’s jurisdiction. For such purpose, the Borrower shall:
with respect to its business activities:
a)
comply with international standards for the protection of the environment and labour laws, particularly the fundamental conventions of the ILO and the international environmental conventions, in accordance with the applicable laws and regulations of the country in which the Project is being implemented. with respect to the Project:
b)
include in the procurement contracts, and, as the case may be, in the bidding documents, a clause whereby the contracting parties agree, and agree to procure that their sub-contractors (if any) agree, to comply with such standards in accordance with the applicable laws and regulations of the country where the Project is being implemented. The Lender will be entitled to request that the Borrower deliver a report on environmental and social conditions of implementation of the Project;
c)
put in place appropriate mitigation measures specific to the Project as defined within the context of the environmental and social risk management policy of the Project and described in the ESCP referred to in the IBRD Loan Agreement.
d)
require that the Contractors appointed for implementation of the Project, apply the mitigation measures set out in paragraph (c) above and procure that their subcontractors (if any) comply with all such measures and take all appropriate steps in the event of a failure to put in place such mitigation measures; and
e)
provide the Lender, through the Co-Financier, with annual follow- up reports in relation to the ESCP.