Član 1.4.C Zakon o potvrđivanju Finansijskog ugovora EPS Zeleno finansiranje A između Republike Srbije i Evropske investicione banke – Second and Subsequent Tranches

Section1.4.C

Second and Subsequent Tranches

Without prejudice to the conditions precedent required in respect of all Tranches set out in (All Tranches), the disbursement of each Tranche under , subsequent to the first disbursement, is conditional upon receipt by the Bank, in form and substance satisfactory to it, on or before the date falling 6 (six) Business Days before the Scheduled Disbursement Date (and, in the case of deferment under , the Requested Deferred Disbursement Date or the Agreed Deferred Disbursement Date, respectively), of the following documents or evidence:
a)
except for the Tranches, disbursement of which amounts to the last 10% (ten per cent) of the Credit, evidence that the amount of the Tranche (except for the first Tranche) to be disbursed does not exceed 10% (ten per cent) of the Credit and (i) 80% (eighty per cent) of the proceeds of all previously disbursed Tranches have been allocated to eligible Sub-Projects, as evidenced by Allocation Letters issued by the Bank; and (ii) 50% (fifty per cent) of the proceeds of all previously disbursed Tranches have been effectively paid out towards any expenditure incurred with respect to any allocated Sub-Project under this Credit.
b)
for all Tranches, disbursement of which amounts to the last 10% (ten per cent) of the Credit:
(i)
100% (one hundred percent) of the proceeds of all previously disbursed Tranches have been allocated to eligible Sub-Projects, as evidenced by Allocation Letters issued by the Bank;
(ii)
a list and procurement plan of Sub-Projects that are expected to be allocated under each such Tranche is submitted to the Bank;
(iii)
the Bank being satisfied with the outcome of the ex-post procurement review(s) conducted by the Bank.