Član Section 5.02 Zakon o potvrđivanju Ugovora o zajmu (Projekat solarno-termalne elektrane u Novom Sadu) između Republike Srbije i Evropske banke za obnovu i razvoj – Condition Precedent to Drawdown

Section5.02

Condition Precedent to Drawdown

The following are specified for purposes of Section 9.02(c) of the Standard Terms and Conditions as additional conditions to the drawdown under this Agreement:
a)
the Project Support Agreement, in form and substance satisfactory to the Bank, has been executed and delivered to the Bank;
b)
a Project Implementation Unit has been established by the MoME and the Project Entity with adequate resources and suitably qualified personnel, in form and substance satisfactory to the Bank, and is operational; and
c)
appointment of qualified consultants to support the Project Implementation Unit (in implementing the Project, including procurement, supervision of work, project management and reporting, financed out of WBIF grant funds, with engagement terms that are approved of by the Bank) have been appointed and mobilised to start their assignment, and are acceptable to Bank.