Član Section 5.02. Zakon o potvrđivanju Ugovora o zajmu Program čvrstog otpada u Srbiji, faza III između Republike Srbije i Evropske banke za obnovu i razvoj – Conditions Precedent to First Drawdown of the Loan

Section5.02.

Conditions Precedent to First Drawdown of the Loan

The following is specified as a condition to the first Drawdown of the Loan under this Agreement:
a)
the appointment of an independent engineer for the New Project Entity by the Borrower, acting through the MEP, to supervise works of the Project.
b)
the Environmental and Social Action Plans, Stakeholder Engagement Plans (as defined in each Project Agreement), Land Acquisition and Resettlement Framework (as defined in each Project Agreement), and Livelihood Restoration Plans (as defined in each Project Agreement) (if relevant) for the Project have been agreed; and
c)
the amendment of the Existing Project Agreements and the execution of the New Project Agreement for the Project by the duly authorised parties thereto.