Zakon o potvrđivanju Ugovora o kreditnom aranžmanu br. 0020022188 koji se odnosi na neobezbeđeni zajam do iznosa od 260.000.000 evra uz garanciju UKEF u cilju finansiranja određenih građevinskih usluga od strane Bechtel Enka UK Limited, koji posluje u Srbiji preko Bechtel Enka UK Limited Ogranak Beograd za potrebe privrednog društva ,,Koridori Srbije" d.o.o. Beograd u vezi sa izgradnjom infrastrukturnog koridora autoputa E-761 deonice Pojate-Preljina (Moravski koridor) između Republike Srbije, koju zastupa Vlada Republike Srbije, postupajući preko Ministarstva finansija, kao Zajmoprimca i J.P. Morgan SE, kao Agenta i JPMorgan Chase Bank, N.A., London Branch, kao Prvobitnog ovlašćenog vodećeg aranžera i Credit Agricole Corporate and Investment Bank i Ing Bank N.V., kao ovlašćenih vodećih aranžera i Određenih drugih finansijskih institucija, kao Prvobitnih zajmodavaca

Status propisa

Na snazi

Prikazana Verzija

Nema dostupnih verzija

Opšte Informacije

DonosilacNarodna skupština Republike Srbije

Zakon o potvrđivanju Ugovora o kreditnom aranžmanu br. 0020022188 koji se odnosi na neobezbeđeni zajam do iznosa od 260.000.000 evra uz garanciju UKEF u cilju finansiranja određenih građevinskih usluga od strane Bechtel Enka UK Limited, koji posluje u Srbiji preko Bechtel Enka UK Limited Ogranak Beograd za potrebe privrednog društva ,,Koridori Srbije" d.o.o. Beograd u vezi sa izgradnjom infrastrukturnog koridora autoputa E-761 deonice Pojate-Preljina (Moravski koridor) između Republike Srbije, koju zastupa Vlada Republike Srbije, postupajući preko Ministarstva finansija, kao Zajmoprimca i J.P. Morgan SE, kao Agenta i JPMorgan Chase Bank, N.A., London Branch, kao Prvobitnog ovlašćenog vodećeg aranžera i Credit Agricole Corporate and Investment Bank i Ing Bank N.V., kao ovlašćenih vodećih aranžera i Određenih drugih finansijskih institucija, kao Prvobitnih zajmodavaca

5.Čl. 5.1–5.2

CONDITIONS OF UTILISATION

Clause5.1

Initial conditions precedent

a)
The Agent shall not give effect to any Utilisation Request unless:
(i)
the Effective Date has occurred;
(ii)
the Agent has received all of the documents and other evidence
listed in Schedule 2 (Conditions Precedent to Initial Utilisation) in a
form and substance satisfactory to the Agent (acting on the
instructions of all Lenders in respect of the conditions set out in
paragraphs 5 and 6(a) of Schedule 2 (Conditions Precedent to Initial
Utilisation)) within thirty (30) days of the Effective Date or by such
later date as the Agent may notify the Borrower;
iii)
the Borrower has complied with its obligations under
(UKEF Support Fee); and
iv)
the Agent has notified the Borrower and the Lenders that the
conditions precedent referred to in paragraphs (i), (ii) and (iii) above
have been satisfied (the "CP Satisfaction Notice").
b)
Other than to the extent that any Lender notifies the Agent in writing to the
contrary before the Agent serves a CP Satisfaction Notice, the Lenders
authorise (but do not require) the Agent to give that notification. The Agent
shall not be liable for any damages, costs or losses whatsoever as a result
of giving any such notification.
c)
The conditions precedent described in Schedule 2 (Conditions Precedent to
Initial Utilisation) are for the benefit of the Agent and the Lenders and the
Agent may waive any or all of those conditions precedent in whole or in part
and decide when and if each of those conditions precedent has been
fulfilled to its satisfaction.
d)
If the conditions precedent referred to in paragraph (a) above are not met
within thirty (30) days of the Effective Date or any later date as the Agent
may agree, the Agent may notify the Borrower that the Commitments of the
Lenders shall be cancellable on notice.
e)
Without prejudice to the generality of (UKEF Guarantee), the
obligation of the Agent to deliver a CP Satisfaction Notice as set out in this
shall be subject to the overriding right of UK Export Finance in
the UKEF Guarantee to determine whether the initial conditions precedent
have been fulfilled or waived to the satisfaction of UK Export Finance.
Clause5.2

Further conditions precedent

a)
Subject to paragraph (b) below, the Lenders shall only be obliged to comply
with (Lenders' participation) if on the date of the Utilisation
Request (if applicable) and on the proposed Utilisation Date:
i)
no Default is continuing or would result from the proposed Loan;
ii)
the Repeating Representations to be made by the Borrower are
true;
iii)
no External Financial Indebtedness is due and unpaid;
iv)
no event described in (Illegality), 8.2 (Material Export
Contract Change), 8.3 (Loss of UKEF Guarantee) or 8.4 (E&S
Incident) has occurred;
v)
the Export Contract is in full force and effect, and has not been
terminated, suspended or amended (other than as permitted under
this Agreement) and no action is proceeding which might lead to the
termination or suspension thereof;
vi)
the UKEF Guarantee is in full force and effect;
vii)
no Sanctions Laws and Regulations would apply to or otherwise
affect the Buyer, the receipt by the Borrower, the Buyer or any
Exporter (as the case may be) of proceeds from a proposed Loan
and or the incurring of debt in relation to a proposed Loan;
viii)
it would not be unlawful or contrary to any Sanctions Laws and
Regulations applicable to a Lender for the proposed Loan to be
made;
ix)
UK Export Finance has received the full amount of the UKEF
Support Fee;
x)
if the proposed Utilisation pursuant to a Utilisation Request is a
Reimbursement Request or a Payment Request, the
representations made by the Exporter in the Exporter Receipt or the
Exporter Payment Request, as appropriate, are true;
xi)
if the proposed Utilisation Request is a Reimbursement Request,
the amount requested does not include any amount in respect of
payments made by the Borrower under the Export Contract to the
Exporter which form part of the cash down payment referred to in
the condition precedent in paragraph 4(d)(i) of Schedule 2
(Conditions Precedent to Initial Utilisation) of the UKEF-Supported
Facility Agreement 2021;
xii)
the Borrower has provided copies of all relevant Authorisations
relating to the proposed Loan including, without limitation, evidence
of the inclusion of the proposed Loan in the relevant annual budget
law of the Republic of Serbia; and
xiii)
there has been no event or circumstance that in the opinion of the
Majority Lenders constitutes or may constitute a material adverse
change in the Relevant Jurisdiction or in its international financial,
economic or political or social conditions, including any sovereign
risk downgrading of the Relevant Jurisdiction by an international
agency and/or deterioration in financial sector of the Relevant
Jurisdiction, war, civil war, revolution, uprising, acts of terrorism
and/or sabotage, an extension of exchange controls or a debt
moratorium, or a change in law or regulation or in the political,
economic, financial, commercial, legal and fiscal environment of the
Relevant Jurisdiction, and which in the opinion of the Majority
Lenders would make it inadvisable to proceed with the Utilisations.
b)
Each Lender may, acting at its discretion, decide to make its participation in
each Loan available in accordance with (Lenders' participation)
regardless of:
i)
whether the conditions set out in paragraph (a) above have been
met; or
ii)
the delivery of notice to the Borrower under paragraph (c) of Clause
20.14 (Acceleration).
c)
If any Loans are made when one or more of the conditions referred to in
paragraph (a) above have not been met or after delivery of notice to the
Borrower under paragraph (c) of (Acceleration), such Loans
shall be repayable by the Borrower on demand by the Agent on the
instructions of the Majority Lenders.