DonosilacNarodna skupština Republike Srbije

Član Section 2.02. Zakon o potvrđivanju Ugovora o garanciji EPS Revitalizacija Vlasinskih HE između Republike Srbije i Evropske banke za obnovu i razvoj – Project Completion

Section2.02.

Project Completion

Whenever there is reasonable cause to believe that the funds available to the Borrower will be inadequate to meet the estimated expenditures required for the carrying out of the Project, the Guarantor shall promptly take measures satisfactory to the Bank to provide the Borrower, or cause the Borrower to be provided, with such funds as are needed to meet such expenditures and requirements.