Zakon o potvrđivanju Finansijskog ugovora Klinički centri faza II između Evropske investicione banke i Republike Srbije

Status propisa

Na snazi

Prikazana Verzija

Nema dostupnih verzija

Opšte Informacije

DonosilacNarodna skupština Republike Srbije

Član 6.6 Zakon o potvrđivanju Finansijskog ugovora Klinički centri faza II između Evropske investicione banke i Republike Srbije – Additional Undertakings

Article6.6

Additional Undertakings

The Borrower, acting through the Ministry of Health as Promoter (where applicable), shall:
a)
ensure that, to the Bank’s satisfaction, the PIU is created and maintained under the Ministry of Health during the entire term of the Contract. The Borrower, acting through the Promoter, shall ensure that the PIU is adequately staffed and equipped, in line with the terms of reference agreed with the Bank, with qualified and dedicated personnel, and supported and advised as necessary by suitable technical assistance, whereby the personnel shall include at minimum the following expertise: (i) project management; (ii) procurement specialist; (iii) engineering specialist (covering both construction and medical equipment); (iv) hospital services planning specialist; (v) financial and contract management specialist; (vi) any additional qualifications, if and as needed during Project implementation;
b)
maintain a Steering Committee during the whole duration of the Project, composed as described under Interpretations and Definitions Section hereto;
c)
at the request of the Bank, promptly provide an updated forecast of expenditures for the whole duration of the Project;
d)
not make any expenditures for new construction works until it has provided to the Bank a copy of the building permit in relation to the relevant construction works;
e)
at Project mid-term (30th June 2028), provide a comprehensive Human Resources and Training Plan for each clinical centre forming part of the Project, elaborating the future service capacity by main specialisation, the staffing structure for efficient operation, a recruitment and training strategy, and the operating cost budget for implementation of the respective plan.
B. GENERAL UNDERTAKINGS